SECTION 321316.15
LITHOCRETEÒ ARCHITECTURAL CONCRETE PAVING
PART 1 GENERAL
1.1 GENERAL
CONDITIONS
A. Requirements
of "General Conditions of the Contract" and of Division 1,
"General Requirements," apply to work in this Section with same force
and effect as though repeated in full herein.
1.2 SCOPE OF
WORK
A. Furnish
materials, labor, transportation, services, and equipment necessary to furnish
and install Lithocreteâ architectural concrete paving incorporating
the patented Lithocreteâ process as indicated on
Drawings and as specified herein.
B. Work
included in this Section:
1.
Installation
of architectural concrete paving called Lithocreteâ under U.S. Patents
2.
(#4,748,788,
#6,033,146, #6,016,635 and U.S. Trademark #1,873,329). Contact Ron Shaw, Paul Taylor, Damon Toth or Ryan Rood @ 949 642 0660
C. Work
related in other Sections:
1.
Section
02750 - Portland Cement Concrete Paving:
Adjacent concrete paving.
2.
Section
02810 - Irrigation System:
Coordination of irrigation sleeve installation.
3.
Section
02900 - Landscape Planting:
Coordination of plant material placement.
4.
Section
07900 – Joint Sealers:
Installation of caulking.
1.3
REQUIREMENTS
OF REGULATORY AGENCIES
A. Federal, State and local laws and regulations governing this Work are hereby incorporated into and made part of this Section. When this Section calls for certain materials, workmanship, or a level of construction that exceeds the level of Federal, State, or local requirements, provisions of this Section take precedence.
1.4 APPLICABLE
STANDARDS
A. Specifications
and recommended practices of American Concrete Institute (ACI), American
Society for Testing and Materials (ASTM), The Uniform Building Code, and U.S. Patent’s #4,748,788, #6,033,146, #6,016,635 and
U.S. Trademark #1,873,329). referred to in this Specification with their individual
designations are to be considered part of this Specification.
B. Design
and Control of Concrete Mixtures – Thirteenth Edition; Portland cement
Association.
1.5 QUALITY
CONTROL
A. Quality
control to be maintained by licensed installers of Lithocreteâ throughout duration of project.
B. Paving
Subcontractor Qualifications: provide evidence to indicate successful
experience in Paving Subcontractor Qualifications: provide evidence to indicate
successful experience in providing Lithocrete similar to that specified herein
and demonstrate successful experience
C. Demonstration
of experience: provide a minimum of 3 local projects with in a 100 mile radius
Of project site of installed Lithocrete architectural paving totaling at least
200,000 s.f. with reference list of each
containing contact person and phone # of project architect’s and owner rep.
D. Supervision:
On site superintendent must have a minimum of 5 years experience installing
Lithocrete.
E. Slip
Resistance: provide a finish with a slip resistance of equal or greater than
0.65 when tested by the owner in accordance with ASTM F 489
1.6 SITE INSPECTION
A. Verify
conditions at site that affect work of this Section.
B. Take
field measurements as required.
C. Report
major discrepancies between Drawings and field dimensions to Owner's Authorized
Representative prior to commencing work.
1.7 SUBMITTALS
A. Product
Data: Submit no later than 10 days
after contract award a typed list of products specified in this Section.
B. Shop
Drawings:
1. Submit
shop drawings for reinforcing steel and accessories in accordance with ACI
standards.
2. Paving
Jointing and Pour Sequence Plan - submit six blueprints indicating the
following:
a. Proposed
layout of contraction, construction and isolation joints. Clearly delineate the three different
joint types.
b. Layout
of paving types as indicated on Drawing Paving Schedule. Give overall dimensions of each paving
type.
c. Concrete
pour sequence. Indicated sequence
of paving pour installation.
C. Statement
of Mix Design: Submit (1) copy of
Statement of Mix Design prepared by batch plant servicing Project for each load
delivered to Project. Statement of
Mix Design to contain following information:
1. Name,
address, and telephone number of batch plant preparing
2. Date
of mix design.
3. Project
location.
4. Contractor
requesting load delivery.
5. Mix
design number.
6. Integral
color used.
7. Gradations
for sand and aggregate.
8. Material
weights, specific gravity, and absolute volumes.
9. Basis
of testing, i.e. UBC 2605 D4 and Title 24 2604 D4.
10. Water/cement
ratio.
11. PSI
rating.
12. Signature
of testing laboratory manager.
13. Signed
stamp from registered Project structural engineer or architect.
D. Lithocreteâ Surface-Seeded Aggregate (extra
stock):
1. One
1-pound sample of each Lithocreteâ aggregate specified.
2. One
100-pound sealed bag of each Lithocreteâ aggregate specified for use by
Owner in future repairs of damaged Lithocreteâ concrete paving.
E. Washed
Concrete Sand (extra stock):
1. One
50-pound sealed bag of washed concrete sand similar to type used during installation
of Lithocreteâ.
1.8 SUBSTITUTIONS
A. None
allowed unless approved in writing by Owner’s Authorized Representative.
1.9 TESTING
A. A
testing agency may be designated by Owner or Owner's Authorized
Representative. Testing personnel to
meet ASTM E329 requirements.
1.10 MOCK-UPS
A. Prior
to construction, provide (1) 4-foot x 4-foot x 4-inch sample of each Lithocreteâ paving type specified on
Drawings.
B. Ensure
that each mock-up contains joint types specified on project, i.e. construction,
contraction, and isolation.
C. Locate
mock-ups in a conveniently accessible and protected place. Approved mock-ups will be standard for
future Lithocreteâ installation review.
D. Remove
mock-ups from site upon completion of Work and approval by Owner’s
Authorized Representative.
1.11 PROJECT CONDITIONS
A. Keep
Work area clean, and in a safe and workmanlike condition so that rubbish, waste
and debris do not interfere with work of other trades.
1.12 PRODUCT HANDLING
A. Store
materials in a dry and protected location. Protect reinforcing steel and dowels from rusting,
deformation, staining, and moisture damage.
B. Keep
Lithocreteâ aggregate dry at all times prior to
installation.
1.13 COORDINATION
A. Notify
Owner’s Authorized Representative and contractors performing work related
to installation of Contractor’s Work in ample time, so as to allow
sufficient time for them to perform their portion of work.
PART 2 PRODUCTS
2.1 PORTLAND
CEMENT
A. Type
I, IA, II, IIA, III, IIIA, IV, and V cements, to conform to ASTM C150.
B. Use
same brand of cement from single source throughout entire project.
C. Refer
to Drawings for cement type specified.
2.2 WASHED
CONCRETE SAND
A. Clean,
hard, and durable washed concrete sand, conforming to ASTM C33.
B. Use
same sand from single source throughout entire project.
2.3 COURSE
AGGREGATE
A. Clean,
hard, and durable coarse aggregate, conforming to ASTM C33.
B. Use
same aggregate from single source throughout entire project.
2.4 LITHOCRETEâ SURFACE-SEEDED AGGREGATE
A. Refer
to Drawings for specified Lithocreteâ surface-seeded aggregate type,
size, color, and distribution percentage.
B. Use
same Lithocreteâ surface-seeded aggregate from same
source for each paving type specified throughout entire project.
2.5 WATER
A. Free
from deleterious materials such as oils, acids, and organic matter.
2.6 ADMIXTURES
A. Integral
Concrete Coloring Admixture: Refer
to Drawings for color type and manufacturer.
1. Acceptable
Manufacturers:
a. L.M.
Scofield; (800) 800-9900.
b. Colorfull
by Admixtures, Inc.; (626)
357-3263.
c. QC; (800) 453-8213.
B. Air
Entrainment Admixtures: Conforming
to ASTM C260.
1. Acceptable
Manufacturers:
a. Grace
Construction Products; DaravairÒ, (800) 433-0020 or www.graceconstruction.com/concrete/air_entraining.html#daravair.
b. Master
Builders, Inc.; Micro-AirÒ, (800) 628-9990 or www.masterbuilders.com/MB/pub/Product.asp?TypeCat=2&ParentID=78&ProductID=22.
C. Water
Reducing Admixtures: Conforming to
ASTM C494, Type A.
1. Acceptable
Manufacturers:
a. Grace
Construction Products; WRDA® (800) 433-0020 www.graceconstruction.com/concrete/water_reducers.html#wrda.
b. Master
Builders, Inc.; Micro-AirÒ (800) 628-9990 or www.masterbuilders.com.
D. Shrinkage
Reducing Admixtures: Conforming to
ASTM C157.
1. Acceptable
Manufacturers:
a. Grace
Construction Products; Eclipse® (800) 433-0020 or www.graceconstruction.com/concrete/shrinkage_reducers.html#eclipse.
b. Eclipse®
Shrinkage Reducing Admixture is a liquid admixture which dramatically reduces
concrete shrinkage and curling due to drying.
2.7 READY
MIXED CONCRETE
A. Batched,
mixed and transported in accordance with ASTM C94 - "Specifications for
Ready Mixed Concrete."
2.8 REINFORCING
A. Reinforcing
Steel: Conforming to ASTM A615,
clean and free of rust, dirt, grease or
oils.
B. Tie
Wire: 16-gauge plain cold-drawn
steel conforming to ASTM A82, clean, and free of rust, dirt, grease or oils.
C. Supports
for Reinforcement:
1. Provide
supports for reinforcement including bolsters, chairs, spacers and other
devices for spacing, supporting and fastening reinforcing bars in place.
D. Polypropylene
Fiber Reinforcement: 100% virgin
multifilament polypropylene fibers, complying with ASTM C 1116 - Type III.
1. Acceptable
Manufacturers:
a. Fibermesh; Fibermix StealthÒ – 1/4” long
(423)892-8080 or www.fibermesh.com/family/stealth.htm.
b. Grace
Construction Products; MicroFiberTM
(800)433-0020 or www.graceconstruction.com/concrete/fibers.html
2. Application
Rate: 1/2 lb./cy of mix.
2.9 ISOLATION
JOINT MATERIALS
A. Refer
to Section 07900 – Joint Sealers for isolation joint construction.
2.10 CONSTRUCTION
JOINT DOWELS
A. Construct
Speed Dowel Construction joints at modules not larger than 20’-0” x
20’-0”.
B. Dowel
schedule to match rebar schedule and at a minimum spacing of 18”o.c.
C. 1/2-inch-diameter
smooth dowel, free of dirt, grease, and oils. Encase 50 percent of each
dowel in a Speed DowelTM plastic sleeve to allow parallel lateral
movement of each Dowel. Double check steel dowel to Speed dowel tolerance to
insure snug fit. Contact
Greenstreak at (800) 325-9504 or www.greenstreak.com/speeddowelhome.htm. Or contact local suppliers such as White
cap
2.11 FLY ASH
A. ASTM
C618 - Type F.
PART 3 EXECUTION
3.1 SUBGRADE
A. Subgrade
to meet requirements of project’s soils report.
B. Ensure
that a minimum 4-inch layer of graded washed concrete sand compacted to
95 percent relative compaction is placed over subgrade prior to placing
concrete.
C. Screed
sand to a smooth plane.
D. Ensure
that utilities, including irrigation lines are buried and compacted below
bottom of sand layer.
E. Keep
sand damp prior to placing concrete.
3.2 FORMING
A. Be
responsible for design and engineering of form work as well as its
construction.
B. Ensure
that Work conforms to recommended practice for concrete form work (ACI 347),
latest edition.
C. Do
not exceed 20-feet by 20-feet in a formed construction area.
D. Ensure
that form lumber is new #2 or better grade wood. Do not use used form lumber.
E. Perform
form layout with a digital electronic transit for line layout accuracy.
F. Allow
forms to remain in place long enough to allow concrete to set properly. Remove forms when appropriate.
3.3 DESIGN OF
MIXES AND PROPORTIONING
A. Proportion
and mix of cement, aggregate, admixture and water to attain required plasticity
and strength in accordance with current edition of ACI Manual of Concrete
Practice and PCA "Design and Control of Concrete Mixtures."
B. Concrete
mixtures to be designed by an approved commercial testing laboratory, using
approved materials to obtain specified minimum compressive strength.
C. Concrete
Mix Criteria:
1.
Slump: 5‑inch, with a 1/2-inch slump
differential between successive batches.
Obtain approval from Owner’s Authorized Representative if slump is
outside these parameters.
2. Minimum
PSI Rating at 28 days: 2,500.
3. Cement
quantity per yard of mix:
a. Minimum: 6 sack.
b. Maximum: 7 sack.
4. Water/cement
ratio: 0.65 – 0.67.
5. Sand: 70% of total mix.
6. Pea
gravel: 30% of total mix.
7. Admixtures:
a. Air
entrainment: Do not exceed 2%.
b. Shrinkage
Reducing: Do not exceed 2% by
weight of cement.
8. Fly
ash: Use only when seeding
reactive Lithocreteâ aggregates such as glass and sea
shells.
9. Non-Chloride
Accelerators: Do not use corrosive
accelerators such as calcium chloride.
10. Concrete
Delivery: Use of concrete loads
exceeding 90 minutes from time of batch plant must be approved by Owner’s
Authorized Representative.
11.
Ensure
that batch plant guarantees single source supply for cement, sand, and
aggregate for the entire project.
3.4 LITHOCRETEâ SURFACE-SEEDED AGGREGATE
INSTALLTION
1. Lithocreteâ is a patented paving process. Installation of Lithocreteâ surface-seeded aggregate must be
performed by a licensed Lithocreteâ installer only.
2. Contact
Lithocreteâ at (949) 642 0660 for a licensed
Lithocreteâ installer in project area.
3. Lithocreteâ is installed in accordance with
U.S. Patents . #4,748,788, #6,033,146, #6,016,635 and U.S. Trademark
#1,873,329).
4. Lithocreteâ process incorporates use of
following patented products:
a. Lithocrete
ConditionerTM.
b. Lithocrete
Etch RetarderÒ.
c. LithosealTM
paving sealer.
3.5 JOINTING
A. Refer
to ACI 302 “Guide for Concrete Floor and Slab Construction” for
work under this section.
B. Construction
and Contraction Joints:
1. Sawcut
construction and contraction joints in locations indicated on Drawings.
2. Perform
jointing with a new diamond tip circular saw.
3. Joint
Width: Per Drawings. Do not exceed 3/16-inch in width.
4. Depth
of sawcuts: 1/4th depth of slab.
b. Decorative
Sawcut Joints: Per Drawings.
5. Sawcut
joints in a straight line with no overcutting.
6. Use a hand tool to sawcut up to vertical edges such as walls, steps, curbs and columns. No cutting into vertical surfaces will be allowed.
C. Isolation
Joint Caulking:
1. Install
isolation joint caulking to be installed under Section 07900 – Joint
Sealers.
3.6 CURING
A. After
initial Lithocreteâ aggregate exposure, continuously
sprinkle or fog paving with water for minimum 7 days.
3.7 SEALING
A. Seal
surface of paving using Lithocreteâ Sealer.
B. Follow
Lithocreteâ Sealer directions when applying this
product (sealer must be applied in 3 to 6 coats).
END OF
SECTION